|
|
|
| Home
/ History
/ Portland
and Weymouth / Dorset's Coastal Defences |
| |
| Breakwater Fort Construction |
| |
| Source: Various (please see
Site Credits) |
Click any picture to enlarge
|
|
| |
|
|
|
|
 |
| Original Fort concept sketch |
|
|
The first design
for the Breakwater Fort was prepared at the War Office in 1859.
This showed a masonry tower of three tiers of casemates with
34 guns. Before the foundations were begun borings were made
at the four quarters of the circle forming the site of the Fort
to ascertain the nature of the sea bed. |
| |
|
|
|
|
|
This was considered favourable and circular
staging , resting on piles screwed as far as possible into
the clay, was erected for the purpose of tipping material
to form the foundations. The piles formed concentric circles
of 112 and 56 feet in diameter, and a radial traveller worked
between them. The rubble foundations consisted of the hardest
type of Portland stone, the largest pieces not exceeding 2
tons and the remainder being small chippings, rubble and grit.
Every truckload contained this mixture, which was intended
to be worked together by the action of the waves into a compact
mass.
In 1861 a modified design of only two tiers,
carrying 35 guns, was proposed and the next year drawings
were sent to Portland showing the arrangements for the basement
storey. There were to be 22 radial walls projecting inwards
from an 11 foot thick external wall of Portland stone faced
with granite. As the intended Fort was to be a masonry work
with a large interior parade ground, the materials of the
outer ring were laid with more care than those in the centre.
By the end of 1862 the work had been brought to a level 20
feet above low water.
The first difficulties arose in October 1864.
A portion between some piers had broken away from the remainder
and at one pier a subsistence of 2'10" had occurred. It was
thought that the cause was likely to be a thin hard stratum
or a yielding bottom under the part that had given away, aggravated
by stormy weather. Additional material was placed at the base
of the slope.
Breakwater Fort - further difficulties
Building of the masonry fort would probably
have begun at the end of 1866 but for the uncertainty that
still existed as to the stability of the foundations and that
no plans had yet been approved for the superstructure - so
construction was put off year by year.
|
| |
|
|
|
|
 |
| Fracture |
|
|
 |
| Fractures |
|
|
|
| |
|
|
|
|
|
Ten days of severe storms in January 1867 produced
further cracks in the masonry, and further gales in March
caused a breach in the outer wall. The Royal Engineer in charge
considered that the movement was almost entirely due to the
combined action of the subsidence and consolidation of the
material composing the foundations. At last in 1867 a decision
on the superstructure was made. The Fort was now to be an
iron plated work of much smaller diameter, which would consequently
not rest on the already built masonry foundations. New foundations
were to be prepared by removing the loose hearting from the
centre and replacing it with a solid cylinder of concrete
10 feet thick and 122 feet in diameter. The removal of the
rubble began in 1868 and by the end of 1869 the task was completed.
Meanwhile the settlement continued.
Amended 1869 plans envisaged an armoured fort
in two tiers of casemates mounting 29 guns, with alternative
designs for a single tier or an armament of four turrets.
Turrets had been seriously considered for the Spithead Sea
Forts and even for the Nothe. In view of the concern over
the foundations it was recommended giving up the idea of a
two tier fort.
Breakwater Fort - the armour arrives and
difficulties continues
Another revised plan in 1870 called for a lower
tier of 14 guns supporting an upper tier mounting 7 guns,
and the superstructure was begun on this basis. The upper
tier was afterwards abandoned. The iron skeleton, made by
Jeavons & Co. of Millwall, was assembled in place in 1873.
The armour plating, of three layers each 61/2 inches thick,
was made by Messrs. Brown of Sheffield. It was taken by rail
to Gosport, and then by water to Portland - to the Fort jetty,
where it was unloaded by an overhanging timber gantry with
a traveller. The traveller dropped each piece into a purpose-built
truck resting on four lines of rail which was drawn up an
incline to the outer circle of the Fort, where it was again
picked up by another traveller working on a circular gantry
and placed in position. The spaces between the armour plates
were filled in with fine Portland cement concrete, except
at the gun ports where they were closed by teak.
Subsidence continued to take place as these
massive weights were piled on. The difference of level between
the highest and lowest points of the outer wall was about
11 1/4 inches. In addition to this fresh subsidence began
under the massive superstructure, causing the bed of concrete
to assume a saucer shape and leading to various cracks and
breaks in the masonry. However, by 1878 this movement appeared
to have very nearly ceased. The only extra weights now to
be added were the armament and ammunition, rather less than
1000 tons and, as this was to be evenly distributed, it was
not thought likely to add materially to the subsidence. Concern
was felt, however, about the result of very severe storms,
one in November 1876 having had a marked effect, contributing
to further yielding of the sea bed under the weight of the
work. Another concern was the washing away of the foreshore
on the exposed side. In 1871 this had been brought up to above
low water of spring tides, but by 1878 it was in parts 20'
below that level. The material added in 1870 which had disappeared
was in blocks of no less than 3 1/2 tons and some approaching
6 tons.
|
| |
|
|
|
|
 |
| The first revolving iron gun turret
on the US ironclad, Merrimack |
|
|
 |
| Monitor and Merrimack during the civil
war |
|
|
|
| |
|
|
|
|
|
Breakwater Fort completed at last
By January 1878 the Fort was on the point of
completion, and the armament of fourteen 38 ton guns was expected,
but they had not arrived by 1882. The masonry of the Fort,
like that of the Verne and the Nothe, had been of Portland
stone, but a great deal of work had been done in concrete.
The stone used for the concrete was Portland from various
beds, broken down to the size of road metal, while the sand
mostly came from Moreton, a particularly sharp and clean sand.
All masonry and brickwork was set in Portland cement, not
common lime mortar. Great care had been taken in manipulation
of the concrete and the results by 1878 had proved very satisfactory,
seas having broken with great force on the concrete apron
with no damage whatever being caused.
The Fort was almost instantaneously obsolescent.
Advances in both guns and armour plate meant that it was defective
both in attack and defence. Although spaces had been provided
in the structure of the Sea Forts to add more armour, the
matter does not appear to have been considered, and the heavy
breech loading guns which the French Navy had adopted quite
outranged the Fort's RMLs. The relative uselessness of the
Fort was recognised, and by 1895 six of the RML had been removed,
incredibly from the seaward side.
Records from exercises of 1895 show the Fort
with seven 12.5 inch RML, worked by Royal Artillery and two
6 pdr QF worked by Sligo Artillery Militia. The RML had no
shrapnel shells, and so to be employed against torpedo boats
at night they had to be kept loaded with case shot and laid
with an elevation of 800 yards to be able to fire at a moment's
notice. By 1900 the Breakwater Fort was armed with four 12.5
inch RML, six 12 pdr QF and three machine guns. Temporary
huts were erected on the masonry apron, and an engine and
dynamo for seachlight positions built on the Breakwater. Buildings
for housing and operating boom defence equipment were also
provided. The success of a black and white chequer scheme
in camouflaging Spitbank Fort led to all the sea forts, including
Breakwater Fort, being similarly treated as a consequence,
and the Portland example is still popularly referred to as
Chequer Fort. A War Office Committee visited the Fort in 1905
and recommended mounting two 6 inch guns on top of the Fort
and two more in the casemates - however it was decided to
mount the two latter on the heads of the new arms of the Breakwater.
The QF were to go. In 1907 the removal of the 12.5 inch guns
began, and measures were taken to emplace two 6 inch BL on
the roof. By 1909 two 6 inch had been mounted there.
|
|
| |
| |
| TOP |
| |
|
|
 |
© Copyright 2003 · Cyberport Project Ltd · All Rights Reserved · Site design by CoDesign |
|
|
|
|
|
|
|